This projecft was the addition of one calssroom for all day Kindergarten at Ridpath Junior Public School. The project required us to tie into the existing services and make sure that the facilities were operational for Labour Day which coincides with the start of school.
This project was the addition of one classroom for all day Kindergarten at Norwood Dstrict Public School. The project required us to tie into existing services and make sure that the existing school was operational for Labour day.
This project was an addition of a new gymnasuim and change rooms at Alexandra Public School. The project was completed while school was still underway. We were required to coordinate our efforts with the school staff and principal to reduce the disruption to the students playing area; whilst keeping and maintaining a safe enviroment.
General upgrades at the school including doors and hardware washroom modifications for accessibility along with new acoustical tile ceilings and flooring.
This project involved the upgrade of classroom millwork and other finishes at four different schools. The projects were completed on time for school to begin.
This project involved the replacement of their HVAC systems at the Lindsay Campus. The project had to be completed while the building remained operational. There was extensive coordination required in order to insure equipment would fit within the existing conditions.
General-Contractor