Naples, Florida
Construction-Management
• Two phased project
Phase 1: Two story new technical / vocational center that included nursing, dental, and culinary arts program
Phase 2: Main building renovation and new construction of classrooms
• Project fast tracked - December 1996 new building construction started; completed on schedule, August of 1997; renovation of existing classrooms started in June 1997 and was completed on schedule, August 1997