Boney Falls Embankment Improvement

General-Contractor

Story

UPPCO contracted Moyle Construction to rebuild both the East and West embankments at their Boney Falls power generating reservoir. Work consisted of approximately 90,000 cubic yards of mass excavation and grading, concrete core wall repairs, and pressurized bedrock grouting. Moyle produced the rip rap needed for the mile long East embankment on-site utilizing their mobile crushing equipment. Temporary structural steel bracing was also required to support the existing concrete core wall during construction.  

Facts

  • Title: Boney falls embankment improvement
  • Phase: Complete


Project Identification Number:

PP-CST-ECC6-72C0-3500-C3EC-0


Status: Completed


Tags

  • other
  • current-projects
  • infrastructure


@Mentions:

Moyle, Inc.

General-Contractor


Worked on this project?

Add it to your portfolio