East Muskegon Roofing and Sheet Metal was hired for the roofing portion of the project. This project brought several challenges. We worked on a very small site in a residential area with an extremely aggressive time frame and an extensive roofing system.
The roofing system starts by priming and installing a vapor barrier on the new concrete roof deck. Then there are layers of insulation set in a foam adhesive. The membrane layers are a multi-ply SBS system set in cold adhesive. Finally there is a white coating applied. This system qualifies for LEED credits. This is a LEED certified facility.
We worked closely as a team with the construction manager, architect, owner, and other trades to ensure keeping with the establised schedule and all the proper safety precautions.
Facts
Title: Spectrum health corporation blodgett campus addition