Grand Rapids, Michigan
Engineering
Design Program: Byce & Associates, Inc. provided mechanical, electrical and structural engineering services for the existing facility to provide a new front-end medium-voltage distribution switchgear, and replacement of the degraded medium-voltage primary cable.
Design Challenges: This project was unique because this plant processes approximately fifty million gallons of wastewater a day and must be kept operational at all times. The construction activities required close coordination with the owner in order to prevent any interruption of service.