ABC Greater Michigan Chapter Awards

Corteva Lyte 10

Midland

Story

Corteva, specializing in agriculture and crop protection, erected Project Lyte 10 in Midland to increase the production of its leading product. In total, 92,753 linear feet (17.5 miles) of process piping and 5,780+ valves were installed to complete this significant project.

Facts

  • Location: Midland
  • Postal code: 48640
  • Budget: $48,850,000

Project Credits:

Three Rivers Corporation

Process Piping

Troy Sullivan

Supervisor

Chad Cooper

Supervisor

Mike Wendt

Supervisor

Drew O'Keefe

Project Superintendent

Drew Schluckbier

Supervisor

Chad Kolba

Supervisor

Chad Feldotte

Supervisor

Travis Arthur

quality

Eric Biskner

Supervisor

Marty Yancer

Supervisor

Jason Quilici

Site Safety Representative

Eldon Keen

quality

Bob Rytlewski

Supervisor

Brett Keidel

Supervisor

Summer Weiss

project management

Tom Sczepanski

project management

Michael Kozakiewicz

project management