ABC - Western Michigan Chapter

Hudsonville Public Schools - 9+ High School

9+ High School Building

Hudsonville, MI

Story

Burgess Concrete was hired to develop and install a consistent "deep aggregate" polished floor to 48,000 SF. The floor was to be on two levels, pouring on grade and topping slab on precast and metal deck. We also needed to make several pours due to schedule and availability of area.

Facts

  • Title: Hudsonville Public Schools - 9+ High School
  • Subtitle: 9+ High School Building
  • Location: Hudsonville, MI
  • Postal code: Hudsonville, MI
  • Budget: 508,209

@Mentions:

Burgess Concrete Construction

Concrete Construction

Triangle Associates

general contractor

Mike Humble

Chief Estimator/Project Manager

Titan Interiors

Interior Finishes

Jim VanBeek

Project Superintendent

Dale Haveman

Project Superintendent

GMB Architecture + Engineering

architectural firm