SWFL International Airport Diesel Tank Replacement

Fort Myers, Florida

Construction-Management

Story

Removed 1000 gallon fiberglass underground diesel tank
Worked with environmental consultant to test soil around existing underground tank for possible contamination, following DEP’s “Storage Tank System Closure Assessment Requirements”
Removed contaminated soil and backfilled with clean
Installed an above ground diesel tank and connected to backup generator
Tested all fuel lines
Installed a 6 ft. high chain link fence around new tank following NFPA requirements
Worked with environmental consultant in submitting the closure assessment report to the county

Facts

  • Title: Swfl international airport diesel tank replacement
  • Location: Fort myers, florida
  • Postal code: 33913
  • Phase: Complete
  • Delivery method: Construction management
  • Size: 1000.0


Project Identification Number:

PP-CST-D4AF-DC8C-B39F-E7AF-0


Status: Completed


Tags

  • airport
  • aviation


@Mentions:

Owen-Ames-Kimball Company - Florida

Construction-Management


Worked on this project?

Add it to your portfolio