C. B. Goldsmith and Associates, Inc.

Clearwater, Florida

Multiple Sites (Memorial Middle, Mort Elem. & Van Buren Elem.) :: Roof Replacement

Florida

Architectural

Story

Re-Roofing: Torch-applied SBS modified roofing over tapered and rigid insulation system over gypsum deck board; roof drain repairs; roof-to-roof ladders; custom flashing and sheet metal; and external gutters and downspouts. Van Buren Middle School: 28,614 sq. ft.; Memorial Middle School: 8,975 sq. ft.; Mort Elementary School: 18,928 sq. ft.

Facts

  • Title: Multiple sites (memorial middle, mort elem. & van buren elem.)
  • Subtitle: Roof replacement
  • Location: Florida
  • Phase: Complete
  • Delivery method: Design-bid-build
  • Budget: $671,000
  • Size: 56517.0


Project Identification Number:

PP-CST-C617-268D-4D77-54A2-0


Status: Completed


Tags

  • k-12
  • educational
  • Roofing


Project Credits:


Worked on this project?

Add it to your portfolio